Apollo Elementary

Apollo Elementary

PROJECT OVERVIEW   
 Apollo Elementary School has various projects to be addressed which are stated in Attachment F.  The attachment is located in the documents section.
 
PROJECT STATUS
Apollo Elementary School is one of the schools on the priority list to be addressed through summer 2017.

Because the cost of the work is estimated to exceed the $2 million threshold for utilizing the District’s continuing service contracts, the work must be awarded through a competitive process. The project will be done through a design build contract, where the successful firm provides construction and final design/permitting services. This process requires the District to develop a Design Criteria Package (DCP) that is prepared by a third party architect (the Design Criteria Professional) who outlines the scope and minimum specifications and/or requirements for the project.

In order to achieve economies of scale and reduce administrative costs, this project will be combined with other schools on this list for implementation over the next two years.

                    FACILITY RENEWAL                                                                                                                                             

51 01          Safety and Building Code Deficiency Corrections                                                             $88,944

52 04          Central Mechanical Plant Renewal                                                                                $578,965

52 05          Cooling and Heating Control System Renewal                                                                 $83,144

52 06          Air Conditioning and Air Distribution Equipment Renewal                                                $754,379

53 08          Exterior Building Wall Finish System Renewal                                                                  $64,091

52 10          Building Water and Sanitary Piping System Renewal                                                        $74,366

54 13          Electrical Distribution System Renewal                                                                          $264,067

                   Facility Renewal Total                                                                                            $1,907,956

                   

                    DISTRICT SCHOOL SECURITY 

                    60 01           Perimeter/Entry Fencing and Gates                                                                                $92,069

                    60 02           Building Access Security Equipment                                                                               $24,335

                                       District School Security Total                                                                                   $116,404

                                                                                                             

                     EDUCATIONAL TECHNOLOGY                                                                                                                        

    65 03          Classroom Technology Infrastructure (Electrical, HVAC, Data)                                          $90,242

                      Educational Technology Total                                                                                     $90,242

                                                                                                                                                                                                       

                         Total All Categories                                                                                               $2,114,602

 

The remaining Educational Technology components will be handled separately.

Project management, administrative and permitting staff time will be charged to the sales surtax fund.


 
PROJECT UPDATE

Purchasing advertised for the Design Build Services on October 26, 2015 and a mandatory pre-proposal meeting is scheduled for November 3, 2015. We anticipate selection and board approval on January 19th, 2016.

On August 25, 2015 Brevard County School Board approved the total project budget for the Design Criteria Professional Services submitted by TLC under their continuing contract for professional services.

PROJECT MANAGER
Arthur Johnson - Project Manager
FUNDING SOURCES
 Project is funded by Half-cent Sales Surtax
 
DELIVERY METHOD
Design Build Contractor will be selected through a Request for Proposal process.
DESIGNER CRITERIA PROFESSIONAL
TLC Engineering for Architecture, Inc.
DESIGN BUILDER
To Be Determined
 

 Documents

Design Criteria Package TLC Engineering for Architecture Apollo.pdfDesign Criteria Package TLC Engineering for Architecture ApolloBREVARDSCHOOLS\Weaver.Debbie
Apollo Elementary - Attachment F.pdfApollo Elementary - Attachment FBowers.Jennie@Facilities