PROJECT OVERVIEW   

The chiller at Atlantis Elementary School failed and was replaced in summer 2015 as an out-of-sequence, contingency project.  The fire alarm and intercom systems are failing and will be bundled with the current educational technology project.

The balance of the facility renewal project at Atlantis is scheduled for the fourth year of the sales surtax program.
 

PROJECT STATUS REPORT

The failed chiller was replaced in summer 2015, funded through capital renewal funds and sales surtax contingency.

A design build contract with Heard Construction, Inc. was approved by the School Board on October 27, 2015 for the educational technology project. The scope of work includes preconstruction design services for structured cabling, student station power/technology HVAC, fire alarm and intercom renewal.

 

PROJECT UPDATE

The chiller replacement project is complete.

The educational technology project is underway. Plant Operations & Maintenance staff have identified fire alarm and intercom components as critical components that need to be addressed. These components are included in the project.

 

PROJECT MANAGER

Christopher Ault - Construction Manager of educational technology project

David K. Martin - Project Manager of the chiller replacement project
 

FUNDING SOURCES

The facility renewal project is funded by a combination of sales surtax and capital renewal funds.  

 

DELIVERY METHOD

For the chiller replacement project, Project Management staff solicited bids from the District's continuing services contract for HVAC mechanical services. Schwenn Services was recommended as the lowest responsive and responsible bidder.

Heard Construction, Inc. was selected as the design builder under their continuing services contract with the District.

 

DESIGNER

The design for the educational technology project will be preformed by Premier Engineering as a subcontractor to Heard Construction, Inc. Project Management staff prepared the Design Criteria Package.

The chiller replacement project was designed by DDC Engineering, Inc.
 

CONTRACTOR

Heard Construction, Inc. is the design builder for the educational technology project. 

Schwenn Services, Inc. was awarded the chiller replacement contract.

 Documents

1- Atlantis Elementary - Attachment F.pdf
1- Atlantis Elementary - Attachment FUse SHIFT+ENTER to open the menu (new window).
6/16/2015 12:53 PMBREVARDSCHOOLS\Lindemann.David
A- Atlantis Project Status Report_ICOC June 17 2015.pdf
A- Atlantis Project Status Report_ICOC June 17 2015Use SHIFT+ENTER to open the menu (new window).
6/16/2015 12:54 PMBREVARDSCHOOLS\Lindemann.David
Atlantis 11x17 Landscape.pdf
Atlantis 11x17 LandscapeUse SHIFT+ENTER to open the menu (new window).
11/4/2015 7:44 AMBREVARDSCHOOLS\Weaver.Debbie
B- Atlantis Exhibit 1_ICOC June 17 2015.pdf
B- Atlantis Exhibit 1_ICOC June 17 2015Use SHIFT+ENTER to open the menu (new window).
6/16/2015 12:54 PMBREVARDSCHOOLS\Lindemann.David
C-Atlantis Summary_ICOC October 21, 2015.pdf
C-Atlantis Summary_ICOC October 21, 2015Use SHIFT+ENTER to open the menu (new window).
11/9/2015 9:56 AMBREVARDSCHOOLS\Weaver.Debbie

 Images

ThumbnailPicture Size
Thumbnail Atlantis Portable Air Unit4000 x 3000
Thumbnail Atlantis Portable Air Unit 24000 x 3000
Thumbnail Atlantis Demo Day4000 x 3000
Thumbnail Atlantis Demo Day 34000 x 3000
(More Items...)

 Calendar

Title
There are no items to show in this view of the "Atlantis Calendar" list. To create a new item, click "New item" above.