Cape View Elementary

Cape View Elementary

PROJECT OVERVIEW   
 Cape View Elementary School has various projects to be addressed which are stated in Attachment F.  The attachment is located in the documents section.
PROJECT STATUS REPORT
 

Cape View Elementary School is second on the priority sales surtax project list based on the priority evaluation system developed in conjunction with the sales surtax referendum.  The estimated cost of the Facility Renewal work is estimated below the $2 million threshold for utilizing the District’s continuing contracts. In preparation for awarding a design build contract for construction in summer 2016, the District engaged Architects RZK, Inc. to prepare the Design Criteria Package (DCP) for the Facility Renewal elements of the Attachment F funded list. The design build process requires the District to develop a Design Criteria Package (DCP) that is prepared by a third party architect who outlines the scope and minimum specifications/requirements for the project.

The DCP will include the following categories:
       

 

       

 

         
  51 03 Fire Alarm System Renewal $9,283  
  52 04 Central Mechanical Plant Renewal $805,410  
  52 05 Cooling and Heating Control System Renewal $108,318  
  52 06 Air Conditioning and Air Distributions Equipment Renewal $377,453  
  53 08 Exterior Building Wall Finish System Renewal $12,084  
  53 09 Exterior Door/Window/Louver System Renewal $18,998  
  52 10 Building Water and Sanitary Piping System Renewal $54,198  
  54 13 Electrical Distributions System Renewal $179,329  
  54 14 Electrical System Components Renewal $55,999  
  54 15  Interior and Exterior Lighting Equipment Renewal $13,611  
         
         
     Total: $1,634,684  
     
The purchase order, in the amount of $20,665 funded by the sales surtax, includes not only the preparation of the DCP but also required services relating to contractor selection and construction administration.

 

The Educational Technology projects have not yet started.

A not-to-exceed design services contract, in the amount of $6,815, has been issued to Harvard Jolly for the District Security projects. This work covers the following categories on Attachment F Sales Surtax Funded Detail Report (Exhibit 1):

         
  66 01 Perimeter/Entry Fencing and Gates $0  
  66 02 Building Access Security Equipment $15,949  
         
    Total: $15,949

 

         
The design fee for the fencing and building access control includes field review and coordination with district security staff and the school principal. The architect will also coordinate with other district staff to ensure that security does not compromise life safety and fire safety codes. The design will provide a menu of access control projects that can be implemented now with the available sales surtax and is easily expandable as additional funding becomes available. The design is funded with sales surtax.

 

Project management, administrative and permitting staff time will be charged to the sales surtax fund for the Facility Renewal, District Security project and Educational Technology projects. These costs have not been posted to the financial system as of June 5, 2015, but will be included on the next report to the ICOC.


 

PROJECT UPDATE
 10/27/15 School Board approved the preconstruction services proposal submitted by Canaveral Construction, Inc. as the design builder for the facility renewal projects. Their proposal is based on the Sales Surtax Funded Detail Report (Attachment F) and the Design Criteria Package (DCP) prepared by RZK Architects, Inc. and DDC Engineering, Inc., which includes work to correct Code deficiencies identified in the DCP and through the District's Building Official and excludes component purchases that do not require design.
 
PROJECT MANAGER
James Hudson - Maintenance Coordinator/Construction Manager
 
FUNDING SOURCES
 Project is funded by Half-Cent Sales Surtax.
 
DELIVERY METHOD
 A Design Build contractor will be selected through a Request for Proposals process.
 
DESIGN CRITERIA PROFESSIONAL
Architects RZK, Inc.
Design Build Services
Canaveral Construction, Inc.

 Documents

1- Cape View Elementary - Attachment F.pdf
1- Cape View Elementary - Attachment FUse SHIFT+ENTER to open the menu (new window).
6/16/2015 1:44 PMBREVARDSCHOOLS\Lindemann.David
A- Cape View Project Status Report_ICOC June 17 2015.pdf
A- Cape View Project Status Report_ICOC June 17 2015Use SHIFT+ENTER to open the menu (new window).
6/16/2015 1:45 PMBREVARDSCHOOLS\Lindemann.David
B- Cape View Exhibit 1_ICOC June 17 2015.pdf
B- Cape View Exhibit 1_ICOC June 17 2015Use SHIFT+ENTER to open the menu (new window).
6/16/2015 1:45 PMBREVARDSCHOOLS\Lindemann.David
C-Cape View Summary_ICOC October 21, 2015.pdf
C-Cape View Summary_ICOC October 21, 2015Use SHIFT+ENTER to open the menu (new window).
11/9/2015 11:15 AMBREVARDSCHOOLS\Weaver.Debbie
Design Criteria Package Architects RZK, Inc. Cape View.pdf
Design Criteria Package Architects RZK, Inc. Cape ViewUse SHIFT+ENTER to open the menu (new window).
4/18/2016 1:08 PMBREVARDSCHOOLS\Weaver.Debbie