Jackson Middle

Andrew Jackson Middle School

PROJECT OVERVIEW   
 Andrew Jackson Middle School has various projects to be addressed which are stated in Attachment F.  The attachment is located in the documents section.
 
PROJECT STATUS
Jackson Middle School is one of the schools on the priority list to be addressed through summer 2017.

Because the cost of the work is estimated to exceed the $2 million threshold for utilizing the District’s continuing service contracts, the work must be awarded through a competitive process. The project will be done through a design build contract, where the successful firm provides construction and final design/permitting services. This process requires the District to develop a Design Criteria Package (DCP) that is prepared by a third party architect (the Design Criteria Professional) who outlines the scope and minimum specifications and/or requirements for the project. The proposal from the Design Criteria Professional is scheduled for School Board consideration on August 25, 2015.

In order to achieve economies of scale and reduce administrative costs, this project will be combined with other schools on this list for implementation over the next two years. The following categories should be included in the project:

 
       FACILITY RENEWAL    
  51 02  ADA Code Deficiency Correction $86,184  
  51 03 Fire Alarm System Renewal

$1,078,782

 
  52 04 Central Mechanical Plant Renewal

$93,116

 
  52 05 Cooling and Heating Control System Renewal

$719,945

 
  53 09 Exterior Door/Window/Louver System Renewal

$15,945

 
  52 10 Building Water and Sanitary Piping System Renewal $53,820  
  52 11 Water Heating System Renewal $32,931  
  54 13 Electrical Distribution System Renewal

$536,179

 
  54 14 Electrical Components (Lightning Protections, Intercom, Generator) Renewal $510,760  
  52 16 Air Supply and Exhaust System Renewal

$32,931

 
    Facility Renewal Total

$3,160,593

 
   

 

EDUCATIONAL TECHNOLOGY

   
  65 03 Classroom Technology Infrastructure (Electrical, HVAC, Data) $101,065  
    Educational Technology Total $101,065  
   

 

Total All Categories

$3,261,658  

 

                                                                                                                                                                                                        

The District Security project and the remaining Educational Technology components will be handled separately.

Project management, administrative and permitting staff time will be charged to the sales surtax fund.


 
PROJECT UPDATE
  Updates will be posted in this section
PROJECT MANAGER
 Arthur Johnson - Project Manager
FUNDING SOURCES
 Project is funded by Half-Cent Sales Surtax
 
DELIVERY METHOD
 A Design Build Contractor will be selected through the Request for Proposals process.
 
DESIGNER/DESIGN CRITERIA PROFESSIONAL
 Design criteria package has been created by TLC Engineering for Architecture, Inc. 
CONTRACTOR
 To Be Determined
 

 Documents

Design Criteria Package TLC Engineering for Architecture Jackson.pdfDesign Criteria Package TLC Engineering for Architecture JacksonBREVARDSCHOOLS\Weaver.Debbie
Jackson Middle - Attachment F.pdfJackson Middle - Attachment FBREVARDSCHOOLS\Weaver.Debbie
Jackson 11x17 Landscape.pdfJackson 11x17 LandscapeBREVARDSCHOOLS\Weaver.Debbie

 Images

ThumbnailPicture Size
Jackson 11x17 Landscape

 Calendar

Title
There are no items to show in this view of the "Jackson Calendar" list. To create a new item, click "New item" above.